Check details with john first – Tear out master bath tile, establish drain placement, reinstall with proper slope (no standing water)
complete window and glazing installation
re-caulk master bath sink basin
Unacceptable Gaps in window installations – John will fix with carpenter seperately
Dining Room Bath Door – Does not Close!
Master bedroom – very slow shower drain
clean all excess grout and smearing from all master bathroom walls
finish plastering/painting kitchen ceiling, tell the electrician to use a dropcloth for dust, and to clean up after himself – he left a huge and unnecessary mess yesterday that I had to clean up and I was pissed – laziness.
Set up appointment with True TV Cable for installation and 5 TV boxes with remotes – ask Cable TV guy about this.
drill small hole in Front room Granite for TV cabling – determine and check placement of this hole with me before drilling it.
final coat polyurethane on stairs (after the conscrtuction is done)
Master bed room toilet upper tank is loose
3rd request – hang master bath door properly – no self-closing.
install mirror master bath
install front door lock
rear bathroom water heater not working – but proper hose fittings (Sam)
Master Bathroom install plumbing fixtures
install new locks – rear bedrooms
Confirm Master Bath Venting is proper (that vent tube is attached to vent on outside)
install magnetic door stop master bath door
AFTER Windows are Hung Properly (John to fix)- make window lock shims, pre-drill holes so it doenst crack wood, go out and purchase proper size screws for the job (security), not whatever may be lying around
Paint crown molding brown in second bedroom
Install base molding to front room woodwork
Smooth out rough plaster work Master bedroom
Remove tile baseboard rear bedroom, plaster, repaint
Order rubber tile for rear bedrooms
Paint INSIDE of all windows White semi gloss (NOT OUTSIDE)
Are contractors/workers leaving any spare tiles behind (both rubber and ceramic)?
Rubber tiles need to go under baseboards – not butt up to baseboards – pull baseboards if necessary and reinstall after tiles are installed.
The baseboards were installed before the floors were put in – why, I cannot say, it should have been done … Read the rest
Install new kitchen door lock (will be provided)
install quarter rounds to all 1st floor windows, paint with primer
dining room – ceiling needs WHITE paint per Spec, walls get 2nd coat.
2nd coat of paint – Thai Kitchen/ rear area
install dining room ceiling fan
All Walls Properly Prepared before Painting!!
ceiling fan is not installed level.
Master Bedroom Light not installed flush with ceiling, clean blemish on glass, install decorative cap
Urgent – Standing water, slope problem in master bathroom
Move Dad’s bed into his bedroom – after floor install
Top-to-Bottom House cleaning!
Window handle and bolt installation – must be done precisely!!
messy paint work!
Determine Exterior Paint color number?
Add trim molding to window to cover gap created by hinge installation.
Clean Paint from AC line, consider painting to match wall color.
vacuum all dust from inside soffit after plaster work
Thoroughly clean dust from AC, top and bottom
Shower fixture is too low – wrong spec, not installed high enough. can this be fixed?
It fine of you are 170cm or less, but it’s too short even for me.… Read the rest